ALBANY – The New York State Public Service Commission Wednesday approved the construction plans for a 5.6 mile 230 kV transmission line along with necessary infrastructure improvements needed for the construction of a 127-megawatt Noble Wethersfield wind farm project in Wyoming County.
In granting final approval of the Environmental Management and Construction Plan, the Commission will allow construction of the substation, the switchyard, access roads and the transmission facility. The transmission line will run from Wethersfield, Wyoming County to Orangeville, Wyoming County.
“Wind farm projects such as Noble Wethersfield, which generate electricity from renewable sources, increase energy diversity and promote a cleaner, healthier environment,” said Commission Chairman Garry Brown. “Approval of the environmental management and construction plan, while taking into account environmental and construction-impact concerns, is an important step for this particular project.”