Cohocton Wind Watch is a community citizen organization dedicated to preserve the public safety, property values, economic viability, environmental integrity and quality of life in Cohocton, NY and in surrounding townships. Neighbors committed to public service in order to achieve a reasonable vision for a Finger Lakes region worthy of future generations.


READ about the FIRST WIND Connection to the Obama Administration

Industrial Wind and the Wall Street Cap and Trade Fraud




********************************************************************

Sunday, November 18, 2012

HECO says Kahuku Wind Farm's battery storage system will cost at least $8M to replace

Hawaiian Electric Co. says its interconnection facility inside the battery energy storage system warehouse at the Kahuku Wind Farm on Oahu's North Shore, which was destroyed by fire in August, will cost at least $8 million to rebuild and take about a year to complete.

The 15-megawatt system, which helps stabilize the wind energy output for the grid, houses both HECO's interconnection facility and Kahuku Wind Farm's control rooms.

The Hawaiian Electric Industries' subsidiary also noted in a letter sent last week to the state Public Utilities Commission that the scheduled completion date for its interconnection facility is late 2013. That means that Boston-based First Wind won't have its Oahu wind farm up and running until the latter part of next year.

Additionally, HECO says that First Wind will replace its battery energy storage system with a D-Var System, a voltage regulation device made by American Superconductor that has proven wind farm experience.

Source

0 Comments:

Post a Comment

Links to this post:

Create a Link

<< Home


Click on link to submit your SEC complaint on the
First Wind Holdings Inc. IPO public offering


TEN Reasons
Why the SEC should not allow First Wind to be listed on NASDAQ

First Wind Holdings Inc. 12/22/09 SEC S1/A IPO Filing

First Wind Holdings Inc. 7/31/08 SEC S1 IPO Filing

May 14, 2010 addition to the First Wind Holdings Inc. SEC S1A IPO Filing

August 18, 2010 amendment 7 to the First Wind Holdings Inc. SEC S1A IPO Filing

October 13, 2010 Filing update to the First Wind Holdings Inc. SEC S1A IPO Filing

New October 25, 2010 Filing update to the First Wind Holdings Inc. SEC S1A IPO Filing


FIRST WIND Lays an Egg WITHDRAWS IPO
after Wall Street no confidence in company




Send email request to join - RIWT Facebook Groupsplus
cohoctonwindwatch@gmail.com

RIWT is open to the public

Risks of Industrial Wind Turbines is a group of citizens and organizations dedicated to preserve the public safety, property values, economic viability, environmental integrity and quality of life of residents and future generations.

**************